La Cañada Unified School District

Skip to main content
Main Menu Toggle
Please Create A Marquee

Requests for Proposals (RFPs 2019)

The RFP for network upgrades is now posted
 
Timeline

RFP Issued

February 13th, 2019

Mandatory walkthrough

February 19th @9am (Email and confirm attendance)

Requests for Information Deadline

February 21st, 2019 by 5pm

Proposals Deadline

March 22nd, 2019 by 2pm

Contract Award

March 27th, 2019 by C.O.B.

 
For questions, please email Jamie Lewsadder (jlewsadder @ lcusd.net)
 
 
Questions and Answers from Bidders
 
Questions:
1) The RFP references verifying quantities, length, etc. on-site. Is there a walkthrough scheduled, or going to be scheduled?

2) The RFP refers to designated Locations as detailed in the approved drawings – but I didn’t see any drawings posted.

3) for Single mode page 17 LCUSD 3. MDF Room:

150m Single Mode Quantity 6 – I’m assuming this is 6 strand Single mode fiber – I don’t see the other end of this fiber connection listed anywhere else. Can you specify where this run is going?

4) for the Multimode fiber (multiple locations in RFP): This appears to be 6 strand fiber – since many of the IDFs have a quantity of 6. Can you please confirm.

Answers:
1) Yes to a walkthrough Tuesday morning at 9am, meeting at LCHS.

2) I'll be giving access to the drawings on Tuesday.

3) I will check on the MDF fiber question.

4) For the 4th question, I believe we mean six strands.  I will confirm

Jamie